in natural gas drilling and production in the Gulf of Thailand
The success confirmed to Onshore Compression Station #2 in 2001
Rental Fleet with option to purchase
To boost the gas of Thailand, in the 4th transmission pipeline.
Onshore Gas Compressor/ PTT OCS#1
EGAT South Bangkok Power Plant Reciprocating Gas Booster compressors : 1800 HP
Problem : Gas Compressor Lock up
Solution : Corrective Maintenance by
coordinating with Dresser Rand Malaysia , USA and Local workshop in Thailand
Completed : Within 22 days ahead of the schedule
This new Gas Turbine model is designed to increase gas transmission force stability and a longer run length from 20,000 hours to 50,000 hours—the exchange is at the Gas Compression Station, Kanchanaburi.